Building work for Amrai Suites, Schruns

Building Construction Tourist buildings

Key data

Country
Austria
Client
Alpstein Chesa Schirun Bau GmbH
Contract value
2,7 Mio. EUR
Construction time
April 2019 - November 2019
Contact

Sekretariat Hochbau
+43 5 7181-1690
E-Mail


JÄGER was commissioned by Alpstein Chesa Schirun Bau GmbH to carry out the master building work for the new Amrai Suites in Schruns.

A modern boutique hotel is being built on the former spa hotel site; in the first instance, in the first phase of construction, a complex with 32 chalets will be realised. The construction of the 6-storey (2 basement floors; 4 upper floors) building, approx. 60 m x 25 m in size, will require the movement of the following masses:

 

- approx. 9,000 m³ excavated material

- approx. 4,000 m³ concrete

- approx. 300 tonnes of structural steel

 

The shell construction work was completed by the end of 2019. The new chalet complex will be ready for occupancy by the beginning of the 2020 winter season.