Vermunt exploration shaft

Underground Mining Power station construction

Exploration shaft for the PSKW Obervermunt

Key data

Country
Austria
Client
Vorarlberger Illwerke AG
Construction method
conventional tunnelling
Contract value
1.3 million EUR
Construction time
January 2010 - January 2011
Excavation diameter / cross-section
13.5 m²
Contact

Sekretariat Untertagebau
+43 5 7181-1190
E-Mail

back to overview