Lower Tuxbach water transfer tunnel breakthrough

The breakthrough at the Tuxertal took place on 14.7.18 after 246 working days and a tunnelling length of 4,444 m. An 80-metre reverse drive had been previously been required for geological reasons.

A festive breakthrough celebration took place in the presence of the Mayor of Mayrhofen, tunnel sponsor Monika Wechselberger, on 16.7.18.