New build finishing/incoming goods area, yarn dyeing plant, warehouse, Bludenz
Building Construction Industry & commerce
Key data
- Country
- Austria
- Client
- Getzner Textil AG
- Contract value
- 4.58 Mio. EUR (as part of a consortium)
- Construction time
- July 2011 - November 2011
- Contact
Sekretariat Hochbau
+43 5 7181-1690
E-Mail
In early July 2011, Getzner Textil AG commissioned the JÄGER–Tomaselli consortium with the task of erecting the shells for the new production sites in the middle of the Getzner company plot.
Within a very short time, 10,000 m³ of concrete and 1,000 tons of steel had been installed. The main work was carried out in 2 shifts per day to adhere to the ambitious schedule.