Power plant Parbati III

Underground Mining Power station construction

Cavern power plant, pressure shaft, underwater tunnel

Project data

Country
India
Client
NHPC Ltd.
Building Method
conventional tunnelling
Burst volume
420.000 m³
Order sum
68.4 million EUR (as part of a consortium)
Period of implementation
January 2006 - January 2011
Diameter / Cross-section
750 - 900 m²
Contact

Sekretariat Untertagebau
+43 5556 7181-817
E-Mail

back to overview